2014Januar

At the plant site of  AGA Gas AB in Stenungsund LAUTEC builds an air separator.

The scope of LAUTEC includes the preparation and installation of the piping system, the insulation, painting, scaffolding and the heavy assembly of the individual components.

As with the project in Norway all the logistics of materials and the pipe spools controlled centrally by Philippsburg.

Commissioning is scheduled for Q3 2014. Client: Linde Engineering Munich.